Established 1980 · ISO 9001:2015 certified since 2017 · Tanzi Dist., Taichung, Taiwan
Progressive stamping die mounted in a press at the YBT plant in Taichung, Taiwan

ODM Solutions

ODM process: from concept to mass production in six stages

Each stage has one deliverable and one decision. You always know what you are approving and what happens if you change your mind.

How long does an ODM project take from first enquiry to first shipment?

The total elapsed time for an outdoor gas appliance is driven by three things that run in sequence and cannot be compressed much: tooling manufacture, certification testing at an accredited body, and the pilot run that validates the assembly line. Design iterations happen in parallel with sourcing, so they rarely sit on the critical path. Certification is usually the longest single block, because the test body schedules the slot and a failed test means a design change followed by a re-test. For that reason YBT reviews the certification scheme for your target market at the feasibility stage rather than after the prototype, so the design is built around the standard from the beginning. The figures YBT publishes are averages from its own programmes: a complete new appliance from first concept through testing and certification to mass production takes about two years; a tooled component needs at least 45 working days to first production and about six months for a full development programme; a part that needs no new tooling can be in production within a week. Once in production, finished appliances ship 45 to 60 working days after order and parts in 1 to 2 weeks, depending on quantity.

The six stages

  1. Stage 1. Requirement review and feasibility

    You provide: your concept, reference product or existing unit, plus target market, target cost and volume. We give you: feasibility summary, open-issue list and the certification scheme that will apply. Decision point: proceed to design. A complete product is quoted within 1 to 2 months of receiving the brief; assemblies within 1 to 2 weeks; simple parts within 3 days.

  2. Stage 2. Concept and engineering design

    3D modelling, material grade selection, gas component specification and design-for-manufacture review by the team that runs the presses. We give you: 3D data, draft BOM and preliminary cost. Decision point: design freeze. Most programmes start from the customer’s drawings; when YBT carries out the design, the development work is quoted separately.

  3. Stage 3. Tooling and prototyping

    Stamping dies, forming fixtures and welding jigs made in house by YBT’s two toolmakers, then a functional prototype. Samples are charged per run and paid in full; work starts once the quotation is signed and returned. Tooling paid for by the customer belongs to the customer. We give you: prototype unit and dimensional inspection report. Decision point: prototype approval. Tooled parts reach first production in at least 45 working days.

  4. Stage 4. Certification testing

    Submission to an accredited body for the target market. We give you: test report and certificate. Decision point: certificate issued. YBT’s existing heaters are certified CE under Regulation (EU) 2016/426 by Intertek Italia (Notified Body 2575) and cETLus listed by Intertek to CSA/ANSI Z83.26, so both routes are in place; the certification block is the main reason a complete new product averages about two years.

  5. Stage 5. Pilot run

    Small-batch build on the production line to validate cycle time, yield, assembly instructions and packaging. We give you: pilot units, yield data and work instructions. Decision point: release to mass production.

  6. Stage 6. Mass production and finished-goods delivery

    Full production, assembly, gas-tightness testing, packing and shipment as complete units with inspection records. Finished appliances ship 45 to 60 working days after order confirmation depending on quantity; terms FOB Taiwan port, payment by L/C or T/T in USD with a deposit on order and the balance before departure; indicative capacity about 3,000 finished units a month.

What do we need from you at each stage?

Customer inputs by stage
StageWhat we need from youFormat
1. FeasibilityConcept or reference product, target market, target cost, annual volumeSketch, photo, sample unit, or written brief
2. DesignBrand requirements, preferred gas components if nominated, packaging directionWritten spec or call
3. Tooling & prototypeWritten design freeze approvalEmail confirmation
4. CertificationConfirmation of the exact market and standard requiredWritten confirmation
5. Pilot runFeedback on pilot units, packaging approvalInspection report or written feedback
6. Mass productionPurchase order, shipping instructionPO and forwarder details

Process questions

What happens if the prototype fails certification?
The design is revised and re-submitted. Because the certification scheme is reviewed at Stage 1 rather than after tooling, the common failure modes are designed out before dies are cut. Re-test costs are handled by cause, in the same way as quality issues: a failure arising from YBT’s construction is YBT’s to correct, a failure arising from a customer-specified design or component is the customer’s.
Can we skip the pilot run to save time?
Not advisable. The pilot run is where cycle time, yield and the assembly instruction are validated. Skipping it moves the risk into your first production container.
Who owns the tooling after the project?
Tooling paid for by the customer belongs to the customer. If production does not reach the quantity agreed in the contract, the tooling design fee is charged separately; there is no refund mechanism against cumulative volume because the customer already owns the tooling.

Start at Stage 1

Send the concept, the target market and an estimated annual volume. That is enough to produce a feasibility summary.

Quotation for a complete product within 1 to 2 months, assemblies in 1 to 2 weeksFinished goods ship 45 to 60 working days after orderNDA signed on request
Start ODM enquiry ODM Solutions overview

Send us your concept or your drawing

Two separate forms, so you are only asked for what applies to your project.

Request a Quote